Monday, March 15

Interior Renovation - Day 0 [Mobilization]

  • Today the foreman ordered the materials needed for the early stage of the interior renovation work.
  • In the evening I provided the orientation to the workers. I informed them of the things to remember while working onsite, including the penalties should they fail to follow the guidelines set by the property developer.
  • For a while I was worried how 50 pieces of 12-foot kiln-dried S4S, along with 30 pieces of 3/4"-thick plyboard and other consummables, will make it from the ground floor to my condo unit. How did they make it to my condo unit? Piece by piece.
  • Except for some vinyl tiles which Mang Rey (the foreman) managed to remove, not much was accomplished today. The workers arrived late onsite because the bus which brought Mang Alejandro, Mang Eric and Jeff from Isabela to Manila broke down. The typical 8-hour journey to Manila was extended to more than half a day. The workers requested to catch up on their sleep in order to have the energy to fully start with the work. I didn't have issues with the request and so I looked forward to the renovation work in full swing starting tomorrow.
Initial set of materials were delivered today
I never thought this much materials will be used