- The frame for the divider that separates the bedroom from the living and dining rooms have been setup today. The 3 skilled workers should now be able to simultaneously work on different areas of the condo - including the roughing in for the lighting, outlets and switches.
- The panels for the double wall were also extended to the section facing east.
- Another set of 34 kiln-dried S4S were delivered today.
- I finally managed to find a way to dispose of the 22 sacks of debris collected during the first 3 days of work. The guys delivering the materials agreed to take the debris with them and then to return the sacks during the next delivery.
Friday, March 19
Interior Renovation - Day 4 [Divide and Conquer]